Process Infrastructure Supply
- Type
- Offsite fabrication & supply
- Programme
- Within programme
- Safety
- 0 incidents
A time-critical turnaround: high-pressure carbon steel piping, stainless sample loops and supports, workshop-fabricated and installed under AIA sign-off.
Dry-run handover window shortened
HSE incidents
Delivered within the turnaround window
Specialised on-site mechanical and structural partner, responsible for procurement, precision workshop fabrication and rapid deployment.
A turnaround window with no slack. On a standard sequence, piping installation waits roughly 48 hours behind teardown of the legacy framework.
Dual-crew, 24-hour shift matching removed that lag. Sample loops were pre-isometried and fabricated offsite, so replacement lines dropped in as the legacy framework came down.
| Materials | High-pressure carbon steel · stainless steel |
|---|---|
| Inspection | Daily Approved Inspection Authority sign-off |
| Execution | Dual-crew 24-hour shifts, offsite pre-isometried spools |
| Disciplines | Piping Systems · Structural Steel · Maintenance & Shutdowns · Engineering & Procurement |
| Records | AIA sign-off logs, Quality Control Packs and client verification records available for procurement review |
Drawings, a bill of quantities or a description of the problem. An engineer reviews every enquiry and comes back to you directly.